To ask the Secretary of State for Defence, what assessment he has made of the adequacy of the contingency budget applied to the Dreadnought programme.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 17th May 2022

The 2015 Strategic Defence and Security Review estimated that the Dreadnought programme is likely to cost a total of £31 billion (including inflation, over the 35 years of the programme) and set a contingency of £10 billion. The programme remains on track to deliver to schedule and within this budget.