Cabinet Office: Buildings

(asked on 10th May 2022) - View Source

Question to the Cabinet Office:

To ask the Minister for the Cabinet Office, with reference to the Answer of 24 May 2021 to Question 3807, on Cabinet Office: Buildings, what progress has been made over the last twelve months on developing plans by the Government Property Agency to refurbish No. 36 Whitehall for use by civil servants; when that building was vacated by its last public service occupants; what the annual cost to the public purse in respect of (a) rates, (b) maintenance and utilities and (c) security relating to that building has been since that date; when he plans to provide the commercially sensitive information referred to in that Answer to the hon. Member for Sutton Coldfield; whether he has plans to visit No. 36 Whitehall; and if he will make a statement.


Answered by
Jacob Rees-Mogg Portrait
Jacob Rees-Mogg
This question was answered on 18th May 2022

The GPA has developed detailed designs for the building to be refurbished for use by Civil Servants. Records indicate the building was vacated in 2012.

As at 31 March 2021:

  • Rates: £0 per annum
  • Maintenance and security costs: £3.5k per annum

From 1 April 2021 to 31 March 2022:

  • Rates: £0
  • Maintenance - principally for one-off urgent Health and Safety works: £724k

I visited 36 Whitehall on 4 May 2022. I have written to my Right Honourable Friend with regards to the letter he was expecting.

Reticulating Splines