National Holocaust Memorial Centre and Learning Service: Costs

(asked on 15th October 2021) - View Source

Question to the Department for Levelling Up, Housing & Communities:

To ask the Secretary of State for Levelling Up, Housing and Communities, pursuant to the Answer of 13 September 2021 to Question 41608 on National Holocaust Memorial Centre and Learning Service, what contracts for the (a) construction, (b) operation, (c) maintenance and (d) security of the Holocaust Memorial and Learning Centre have been signed to date; and what proportion of the estimated total cost has been committed.


Answered by
Kemi Badenoch Portrait
Kemi Badenoch
President of the Board of Trade
This question was answered on 25th October 2021

A contract is in place under (a) construction for enabling works, including redirecting cables, new incoming services, relocating the Spicer Memorial, tree root investigation and pruning. No contracts have been let under (b) operation, (c) maintenance and (d) security.