Railways: Standards

(asked on 6th December 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what the top three main causes of late-running trains on the rail network were in the last 12 months.


Answered by
Paul Maynard Portrait
Paul Maynard
Parliamentary Under-Secretary (Department for Work and Pensions)
This question was answered on 12th December 2016

The top three delay categories for the period 15th November 2015 to 12th November 2016 were as shown below (all in delay minutes):

Network Management/Other 2,713,856

Points, Signalling & Other Non-Track Assets 2,461,412

Technical Fleet Delays 2,141,106

(Other Delays) 7,040,581

Total Delays 14,356,955