Type 45 Destroyers: Guided Weapons

(asked on 20th September 2021) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, which of the six Type 45 Destroyers will be (a) fitted with a Sea Ceptor surface-to-air missile, (b) the first to undergo the fitting of the Sea Ceptor and when and (c) the last to undergo the fitting of the Sea Ceptor and when that fitting will be complete.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 23rd September 2021

Elements of the Sea Ceptor weapon system, including the Common Anti-Air Modular Missile (CAMM), will be integrated into the Sea Viper (SV) weapon system on all six Type 45 Destroyers. On current plans, the first ship is expected to achieve SV-CAMM Initial Operating Capability by early 2027 with the whole fleet rollout completed by the end of 2032. The programme is dependent on the availability of ships to receive the upgrade, balanced against the Royal Navy's standing and future operational commitments.