Question to the Department for Transport:

To ask the Secretary of State for Transport, when he plans that the new platforms at London Bridge Station will become operational.


Answered by
Paul Maynard Portrait
Paul Maynard
Parliamentary Under-Secretary (Department for Work and Pensions)
This question was answered on 7th September 2016

The redevelopment of London Bridge station by Network Rail is progressing to schedule. The new terminating platforms ten to fifteen have been in operation since January 2015 and platforms seven to nine, for services to Charing Cross, became operational on 29 August 2016. The remaining new platforms will be brought into use by January 2018.

Platform six, also for Charing Cross services, will become operational in August 2017. Platforms four and five (for Thameslink services) and one to three (for Cannon Street services) will become operational in January 2018.