National Grid: Development Consent Orders

(asked on 11th November 2026) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, whether she has received a report from the examining authority in relation to the proposed Norwich to Tilbury Great Grid Upgrade.


Answered by
Michael Shanks Portrait
Michael Shanks
Minister of State (Department for Energy Security and Net Zero)
This question was answered on 16th November 2026

The Planning Inspectorate’s Report on the application for development consent for the Norwich to Tilbury project was received on the 10th November 2026.The statutory deadline for taking the decision is three months from this date, being the 10th February 2027.