Govia Thameslink Railway

(asked on 13th June 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, (a) on what dates and (b) by what margins Govia Thameslink Railway has been in breach of the terms of its franchise agreement since the start of that franchise in 2014.


Answered by
 Portrait
Claire Perry
This question was answered on 27th June 2016

Since Rail Industry period 7 in financial year 2015/16 (ending mid October 2015), Govia Thameslink Railway (GTR) have exceeded the breach level for the Cancellations benchmark. The Secretary of State issued GTR with a Remedial Plan Notice last year requiring them to set out in a Remedial Plan the measures they will take in order to improve their performance and included remedial plan benchmarks against which GTR are measured for the duration of the Remedial Plan. GTR have not breached the remedial plan cancellations benchmark and are under the breach benchmark for delays and peak short formations.