Question to the Ministry of Defence:
To ask the Secretary of State for Defence, with reference to the key performance findings on page 7 of the National Audit Office report, Managing infrastructure projects on nuclear-regulated sites, published on 10 January 2020, whether funding will be reallocated from other defence projects to cover the additional £1.35 billion cost increase associated with the three projects examined and reviewed by the National Audit Office.
Like any large organisation we allocate funds to those activities that are the highest priority.
We are committed to strengthening the management of nuclear programmes, including investing significantly in infrastructure and working closely with regulators and industry partners.