Barking Station

(asked on 20th May 2026) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what progress c2c has made on upgrading Barking station since 17 December 2025; and whether the upgraded ticket office, new lift and extended gateline remain on schedule for completion in 2026.


Answered by
Keir Mather Portrait
Keir Mather
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 8th June 2026

c2c continue to make positive progress on the Barking station upgrade. Since 17 December 2025, both gatelines have been installed and are operational, the upgraded ticket office is 95% complete and the lift works are complete with lifts returning to service on 18 May 2026. Remaining works include cladding the gatelines and installation of permanent gateline power. Full completion of the station project is due for autumn 2026, and we will continue to hold c2c to account to deliver by this date.