High Speed 2 Line: Cheshire

(asked on 5th July 2022) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, pursuant to the Answer of 4 July 2022 to Question 26843 on High Speed 2 Line: Cheshire, where in the North West jobs for building Phase 2bWL will be based; and what job roles are included in the figures.


Answered by
Trudy Harrison Portrait
Trudy Harrison
This question was answered on 13th July 2022

Jobs will be created along the line of route, in counties including Cheshire. We do not have any further details of locations at this stage.

The job roles included in the figures previously given for Phase 2bWL include those in both the construction and rail engineering sectors. The peak workforce in 29/30 split for Phase 2bWL is: construction 15,400 FTE and rail engineering 2,500 FTE giving a total of 17,500 FTE.

Construction peaks at around 15,400 people with a relatively constant workforce around that level from 2027/28 to 2029/30. Around 48% of the workforce are in construction operative roles and close to 40% in management roles. Design service roles account for about 13% of the workforce and peak in 2021/22.

In rail engineering, the largest demand for labour and skills occurs in the track asset type, followed by traction and rolling stock, and then signalling systems & telecommunications.

Source document : HS2 Labour and Skills demand and supply forecasting and analysis: July ‘ 21. (Further break down of figures explained on page 37).