Dore and Totley Station

(asked on 16th March 2020) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what his department's expected timescale is for work to (a) start and (b) be completed on restoration of the second platform at Dore & Totley station through National Rail’s Hope Valley Capacity Scheme.


Answered by
Chris Heaton-Harris Portrait
Chris Heaton-Harris
Secretary of State for Northern Ireland
This question was answered on 19th March 2020

Network Rail are part way through a procurement process to appoint a supplier to carry out detailed designs and deliver the scheme. They are working with the train operators to assess the best way to deliver the works during Control Period 6 (2019-2024) with the least disruption to customers. I am expecting Network Rail’s Final Business Case for the scheme over the course of the summer after which I will be able to say more about specific delivery dates of the scheme’s components in the Autumn.