To ask the Secretary of State for Energy Security and Net Zero, how many datacentres are currently in the queue to connect to the National Grid, and what the average expected connection wait time is.


Answered by
Martin McCluskey Portrait
Martin McCluskey
Parliamentary Under-Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 16th September 2026

Data collected in 2025 and published by the National Energy System Operator shows 72.8 GW of capacity allocated to data centres in the GB connection queue across transmission and distribution, with connection dates extending to the late 2030s. It is not currently possible to provide a count of individual projects.

Government recently consulted on measures to manage the current oversubscription of data centre connections and will publish its response in due course.