River Parrett: Flood Control

(asked on 15th May 2024) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the Answer of 1 December 2023 to Question 3315 on River Parrett: Flood Control, whether it remains his timetable for the Bridgwater Tibal Barrier to be operational by early 2027.


Answered by
Robbie Moore Portrait
Robbie Moore
Shadow Minister (Environment, Food and Rural Affairs)
This question was answered on 21st May 2024

The Bridgwater Tidal Barrier project is on programme to deliver an operational barrier by early 2027.