Radioactive Waste: Dalgety Bay

(asked on 5th April 2019) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what radiation remediation works have so far been carried out at Dalgety Bay; what further works are planned ;and when the works are expected to be complete.


Answered by
Tobias Ellwood Portrait
Tobias Ellwood
This question was answered on 15th April 2019

The Ministry of Defence, the Scottish Environmental Protection Agency and Fife Council continue to work together to implement the agreed Management Strategy for the long-term management of radium contamination at Dalgety Bay.

Remediation is due to physically begin in April 2020 and be completed in September of the same year. The second phase of work is planned to begin in April 2021 and be completed in September 2021. Work cannot take place outside of these periods due to the disturbance that may be caused to wintering birds.

Reticulating Splines