Carbon Capture, Usage and Storage

(asked on 29th April 2024) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what assessment her Department has made of the potential impact of using transport and storage companies for the development of provisional cluster expansion plans for Track-2 carbon capture, usage and storage on the timely roll-out of the projects.


Answered by
Andrew Bowie Portrait
Andrew Bowie
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 8th May 2024

The CCUS Track-2 December 2023 Market Update set out government’s proposed Track-2 approach of an ‘anchor’ and ‘buildout’ phase; this embedded learnings from the CCUS Track-1 process. The Track-2 process aims to establish clusters at pace and provide a platform for flexibility and innovation in future phases, as well as to carry out transport and storage sizing.

At ‘anchor’ phase, Acorn and Viking will be invited to submit plans for initial capture projects, as well as a provisional expansion plan for the ‘buildout’ phase. The format of the buildout rounds will be announced in due course and may be subject to factors including project pool maturity and progress against our Net Zero and Energy Security objectives.