Question to the HM Treasury:
To ask the Chancellor of the Exchequer, what progress HMRC has made on its moving its inland pre-clearance operations to new purpose-equipped sites at Hayes and Milton Keynes; and what contingency measures HMRC has implemented to mitigate delays as a result of that move.
HMRC’s new Inland Pre-Clearance sites are now operational. The move resulted in a temporary backlog of consignments for examination. HMRC has triaged consignments using a principled risk-based approach, releasing some consignments without prejudice to any further compliance action, and has also examined other consignments at the port. HMRC is now moving remaining containers from the ports for examination.