High Rise Flats: Insulation

(asked on 19th March 2019) - View Source

Question to the Department for Levelling Up, Housing & Communities:

To ask the Secretary of State for Housing, Communities and Local Government, with reference to the latest Building Safety Programme: Monthly Data Release, how many developments contain the 163 private residential buildings still with ACM cladding systems.


Answered by
Kit Malthouse Portrait
Kit Malthouse
This question was answered on 22nd March 2019

MHCLG have been informed by local authorities and building owners of 163 high-rise residential buildings with Aluminium Composite Material cladding systems unlikely to meet Building Regulations, which are yet to be remediated (at 28 February 2019). Of these, 102 buildings are parts of 31 distinct developments. In total, the 163 buildings span 92 separate developments.