Question to the Department for Energy Security & Net Zero:
To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 5 December 2024 to Question 17189 on National Grid: Costs of the Western and Eastern Links, if he will make an estimate of the time for delivering the onshore option for Eastern Green Link 1 and 2.
At the time of Ofgem’s decision for Eastern Green Link (EGL) 1&2 Final Need Case, an onshore option was expected to be delivered by 2036, based on information provided by the Transmission Owner, National Grid Electricity Transmission. It was not included as part of the Final Need Case,[1] as analysis conducted by the Electricity System Operator found that the reinforcement was needed earlier than the onshore option could be delivered.[2]