Question to the Department for Education:
To ask the Secretary of State for Education, how many and what proportion of school rebuilding projects have (a) been completed, (b) been completed within their intended time frame and (c) have passed their original deadline.
As of 31 December 2024, buildings have been handed over at 23 schools. Of these, demolition and ground works are complete at nine schools, with a further six forecast to reach practical completion this financial year.
The programme started in 2020, with the first projects announced in 2021. In line with initial expectations for the programme, just under half of School Rebuilding Programme projects have commenced various stages of delivery activity, despite some market challenges caused by significant global events. The remaining projects have been given indicative start dates for delivery over the next few years based on a prioritisation of need, with building projects taking up to five years from commencement to complete.