HMS Vigilant

(asked on 11th March 2015) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, how much has been spent on refitting HMS Vigilant in each of the last three years.


Answered by
Philip Dunne Portrait
Philip Dunne
This question was answered on 19th March 2015

The table below summarises the cost of maintenance and refit for the four Vanguard class submarines for the last three financial years.

Total Maintenance Costs

(£ million)

Refit Costs

(£ million)

2011-12

2012-13

2013-14

2011-12

2012-13

2013-14

Vanguard

2.4

4.4

0

0.1

4.1

Vengeance

0.8

0.8

43.5

105.6

119.2

Vigilant

1.8

1.4

74.1

8.0

0.1

Victorious

1.6

1.5

0

0

0

Total

10.6

6.6

8.1

117.6

113.7

123.4

Maintenance costs for the Vanguard Class for financial year 2011-12 cannot be broken down by individual vessels as the information is not held in the format requested.