High Rise Flats: Insulation

(asked on 30th June 2017) - View Source

Question to the Department for Levelling Up, Housing & Communities:

To ask the Secretary of State for Communities and Local Government, if he will issue urgent guidance on what are acceptable replacement materials for the multi-storey blocks that have had cladding removed.


Answered by
Alok Sharma Portrait
Alok Sharma
COP26 President (Cabinet Office)
This question was answered on 20th July 2017

The Building Regulations and supporting guidance set out the requirements for external walls in relation to fire safety. Advice to all building control bodies was published on 14 July, which highlighted the key Building Regulations' guidance requirements when cladding work on high rise buildings over 18 metres tall is undertaken. That note can be found at: https://www.gov.uk/government/news/ensure-that-recladding-work-meets-building-regulations-advises-expert-panel

Reticulating Splines