Question to the Department for Transport:
To ask the Secretary of State for Transport, pursuant to the Answer of 8 February 2019 to Question 216885 on High Speed 2 Railway Line: Buckinghamshire, how long those sites will accommodate construction workers; and whether construction workers' families will also be accommodated on the sites.
Based on the Environmental Statement, the approximate duration for accommodation is 3 years 6 months at the A41 Bicester Road compound and 3 years 9 months at the Small Dean compound. The sites are for construction workers and not families.