Question to the Ministry of Justice:
To ask the Secretary of State for Justice, how much the new contract for electronic monitoring is costing his Department in each year of the contract.
The annual cost of the Ministry of Justice’s new electronic monitoring contracts is forecast as follows:
2015/16 | 2016/17 | 2017/18 | 2018/19 | 2019/20 | 2020/21 |
£114.5M | £81.8M | £61.2M | £59.4M | £56.6M | £56.6M |
The figure for 2015/16 incorporates the cost of mobilising the contracts. We expect the new contracts to deliver average annual savings of approximately £20m relative to the previous contracts with G4S and Serco.
These new contracts will allow us to introduce some of the most advanced electronic monitoring technology in the world. Satellite tagging will allow us to keep a much closer watch on the most high-risk and persistent offenders who cause so much harm in our communities, creating a safer society with fewer victims.