High Speed 2 Railway Line

(asked on 8th January 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, with reference to paragraph 11.10 of the Spending Review and Autumn Statement 2015, whether the figure of £55.7 billion for High Speed 2 is exclusive of the cost of rolling stock for that project.


Answered by
Robert Goodwill Portrait
Robert Goodwill
This question was answered on 18th January 2016

The £55.7bn long-term funding envelope for delivering HS2 includes funding provision for rolling stock.