Question to the Department for Transport:
To ask the Secretary of State for Transport, with reference to paragraph 11.10 of the Spending Review and Autumn Statement 2015, whether the figure of £55.7 billion for High Speed 2 is exclusive of the cost of rolling stock for that project.
The £55.7bn long-term funding envelope for delivering HS2 includes funding provision for rolling stock.