Wind Power: Seas and Oceans

(asked on 16th October 2023) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what estimate she has made of how much new energy generation from offshore wind farms the transmission network between Norwich and Tilbury can sustain.


Answered by
Andrew Bowie Portrait
Andrew Bowie
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 23rd October 2023

The National Grid Electricity System Operator (ESO) is responsible for ensuring the electricity system is operated safely, reliably and efficiently and for managing the electricity market. The ESO sets out the high-level design for the necessary transmission through independent, evidenced based assessment. National Grid Electricity Transmission, as the transmission owner for England and Wales, are responsible for the development of that proposed project. NGET recently published further information on their website related to this matter as part of their latest consultation.

Given the Secretary of State’s role as the decision-taker in the consenting process for nationally significant infrastructure, the Department cannot comment on specific issues regarding a proposed infrastructure project to avoid prejudicing future planning decisions.