Sizewell C Power Station: Finance

(asked on 12th December 2024) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, how much public investment has been directed to Sizewell C in each year since 2022.


Answered by
Michael Shanks Portrait
Michael Shanks
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 19th December 2024

The Government has announced funding provided to Sizewell C in the following financial years: £100m in 2021/22, £679m in 2022/23, £1,811m in 2023/24 and £1,200m in 2024/25 to date.