To ask the Secretary of State for Transport, when the western carriageway of the A46 between Lincoln and Newark was last examined for defects; and when that stretch of carriageway is scheduled to be resurfaced.
The last inspection on the westbound A46 between Lincoln and Newark was conducted on 7 September 2023. National Highways did not identify any safety critical defects during their last inspection.
NH currently has a resurfacing scheme ongoing:
These works are due to be completed in October 2023.
National Highways are also currently in the process of scheduling some short-term road surface repairs between Brough and Hykeham. They currently anticipate these will be completed by the end of 2023.