Question to the Department for Energy Security & Net Zero:
To ask the Secretary of State for Energy Security and Net Zero, what assessment his Department has made of the adequacy of lead times for connecting renewable energy projects to the grid.
Years of world-leading green investment has meant network operators have experienced record demand for connections to the electricity network. We have increased the amount of renewable energy connected to the grid more than sixfold since 2010.
Government is working with Ofgem and network companies to release network capacity and improve the connections process, to accelerate connections. Actions already underway by network companies are expected to see a reduction in transmission connection timescales of 2-10 years, for the majority of existing projects. Building on this work, the Government and Ofgem will publish a joint action plan on accelerating connections this summer.