North Lincolnshire Green Energy Park

(asked on 9th December 2024) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what steps his Department is taking to construct grid connections for North Lincolnshire Energy Park.


Answered by
Michael Shanks Portrait
Michael Shanks
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 16th December 2024

Northern Powergrid (NPg) and National Grid Electricity Transmission are responsible for the construction of the connections. I understand from NPg that the connection infrastructure is expected to be completed in 2027. Energisation dates will be specific to each customer in the energy park.