Question to the Department for Transport:
To ask the Secretary of State for Transport, pursuant to the Answer of 1 July 2026 to Question 12229 on Railways: Infrastructure, what the total number is of rail infrastructure projects in England with an anticipated capital cost of less than £50 million that are currently delivering on site; and what proportion of those projects are forecasting completion after their original baseline completion date.
Of the rail infrastructure projects in England currently delivering on site with an anticipated capital cost of less than £50 million, 144 projects are forecasting completion after their original baseline completion date, out of a total of approximately 500 projects.