Question to the Department for Energy Security & Net Zero:
To ask the Secretary of State for Energy Security and Net Zero, whether his Department is taking steps to help increase grid connectivity for (a) renewable energy generation and (b) battery energy storage.
I refer the hon. Member to the answer I gave the hon. Member for Ynys Môn on 17 April 2023 to Question 176768. The Government works with Ofgem and network companies to accelerate connections by releasing network capacity and improving the connections process. As part of this work, the Electricity System Operator is seeking expressions of interest, by 30 April 2023, from developers who are willing and able to connect earlier than their allocated connection date. The Government will publish a Connections Action Plan in the summer, which will articulate actions by government, Ofgem and network companies to accelerate network connections, including for renewable energy and battery storage projects.