Midland Main Line: Electrification

(asked on 11th March 2024) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what progress his Department has made on the (a) planning and (b) programming for the electrification of the Midland Main Line to Nottingham.


Answered by
Huw Merriman Portrait
Huw Merriman
Minister of State (Department for Transport)
This question was answered on 14th March 2024

Work is already underway to electrify the Midland Main Line (MML) with progress being made to install overhead line equipment between Kettering and Wigston, as well as upgrades south of Bedford to be completed in 2025. During 2024 Network Rail are continuing currently funded design and pre-construction between Wigston Junction north towards Trent Junction, a further 28.4 miles (45.7 route kilometres) of electrification on the MML. Recent plans from Network Rail indicate that electrification of the Midlands Main Line route to Sheffield and Nottingham could be completed in the early 2030s.

Reticulating Splines