National Grid

(asked on 5th March 2024) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, how many projects that have been granted grid access which have (a) stalled and (b) ceased entirely have been removed from the national grid connection queue in the last year.


Answered by
Graham Stuart Portrait
Graham Stuart
This question was answered on 11th March 2024

Data from the Electricity System Operator (ESO) shows that 31 projects have been removed from the transmission connections queue since 1 March 2023. Of these 31 projects, 13 terminated their agreements voluntarily as part of the ESO’s Transmission Entry Capacity (TEC) Amnesty.

As set out at Budget, the ESO has begun the process of inserting delivery milestones into over 1000 connection agreements, enabling it to terminate stalled projects from Autumn 2024. The Government will also work with the ESO and network companies to outline further reforms by summer 2024 to raise barriers to entering and remaining in the queue.

Reticulating Splines