To ask the Secretary of State for the Home Department, how many and what proportion of the recommendations from phase one of the Grenfell Tower Inquiry have been implemented.
The Government published the 6th bi-annual progress tracker on implementation of the Phase 1 recommendations on 29 June on gov.uk and Fire England.
This reported that 31 of the 46 recommendations have been completed overall. This includes the following completion rates:
· 10 out of 15 recommendations for Government.
· 13 out of the 14 for LFB only.
· 1 out of the 9 for all fire and rescue services (FRSs). FRSs have, however, reported completion rates of 91% of their actions on average, but national recommendations cannot be signed off as complete until all 44 services have completed all actions in full.
7 out of 8 for other bodies including other emergency services.
Government remains committed to overseeing the delivery of all of the Phase 1 recommendations. The 7th tracker is due to be published shortly and will report on the further progress made by FRSs and Government.