Lower Thames Crossing

(asked on 21st November 2024) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what recent estimate her Department has made of the (a) cost of preparing and (b) length of the environmental impact assessment for the Lower Thames Crossing development consent order application.


Answered by
Lilian Greenwood Portrait
Lilian Greenwood
Government Whip, Lord Commissioner of HM Treasury
This question was answered on 29th November 2024

Due to the level of interdependency between the large number of different elements of the Lower Thames Crossing Development Consent Order (DCO) application, it is not possible to accurately attribute costs to the production of the individual documents within it. However, the total amount spent on the planning process is £295.1million.

The Environmental Impact Assessment information submitted in 2022 as part of the Lower Thames Crossing DCO application comprised of approximately 12,000 pages.