Leicester Station: Construction

(asked on 14th May 2021) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, dependent on a positive business case, when construction of the Leicester Station four-tracking scheme would commence.


Answered by
Chris Heaton-Harris Portrait
Chris Heaton-Harris
Secretary of State for Northern Ireland
This question was answered on 20th May 2021

Following Network Rail’s publication of Strategic Advice for improving capacity in the Leicester area, which identified a suite of interventions for improvements at Leicester including four-tracking south of the station, they will now produce a Strategic Outline Business Case. We expect to receive the business case by Spring 2022, and it will include proposed delivery dates for the phasing of possible interventions.