Palace of Westminster: Repairs and Maintenance

(asked on 10th December 2020) - View Source

Question

To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what discussions he has had with (a) Ministers and the (b) House of Commons Commission on the effect of the parliamentary restoration and renewal project on congestion in London.


Answered by
Damian Hinds Portrait
Damian Hinds
Minister of State (Education)
This question was answered on 27th January 2021

The Restoration and Renewal Programme is currently creating its business case. Part of this work, once the preferred option has been agreed, will be an environmental assessment on both the construction phase and operations of the restored buildings, where impacts will be assessed and mitigations proposed. To date, no specific conversations have been held on congestion, as the business case work is still in its early stages. The Programme is committed to sustainability and to meeting its environmental obligations.