Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, what assessment he has made of whether cancellation charges incurred by subcontractors and SMEs after 15 January 2018 working on public contracts secured by Carillion will be paid.


Answered by
Andrew Griffiths Portrait
Andrew Griffiths
This question was answered on 20th February 2018

Goods and services supplied with the Official Receiver’s agreement following the making of the winding up orders against Carillion Plc and its subsidiaries will be paid in full. Any amounts due by the Carillion companies to contractors and suppliers prior to the date of the winding-up orders will be claims in the liquidation and included in the general body of unsecured creditors. Those claims in the liquidation could include incidental costs incurred by subcontractors and others which are a direct consequence of the liquidations.