Energy: Finance

(asked on 4th November 2024) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, whether he has made an estimate of the number of unfinanced energy projects in the queue to be connected to the power grid.


Answered by
Michael Shanks Portrait
Michael Shanks
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 11th November 2024

Data on financing of projects in the connections queue is not available. However, National Energy System Operator estimates that historically, 60-70% of transmission connection projects do not ultimately connect, including those that do not secure financing. NESO is currently consulting on proposals that would, if approved, ensure only viable projects are able to obtain and retain a connection agreement.