To ask the Minister for the Cabinet Office, pursuant to the Answer of 29 January 2024 to Question 11390 on Cabinet Office: Ministers' Private Offices, how much was spent on each of those refurbishments.
The Ministerial Offices in 70 Whitehall, redecorated due to water damage in April 2023, cost a total of £19,956.50 exclusive of VAT.
The redecoration of the Ministerial Waiting Room in 70 Whitehall with furniture alterations (partly necessary due to historic mould issues, and completed in November 2023) cost a total of £13,359.11 exclusive of VAT.
The decoration of the Ministerial corridor (due to complete in March 2024) is taking place as part of planned building-wide programme of annual maintenance. As part of this programme, a number of corridors throughout the building are being repainted. Therefore it is not possible to distinguish the cost of the redecoration of the Ministerial corridor from the wider programme.