Railways: Speed Limits

(asked on 13th October 2015) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, how many temporary speed restrictions were in place on Network Rail infrastructure on (a) 1 April and (b) the most recent date for which figures are available.


Answered by
 Portrait
Claire Perry
This question was answered on 16th October 2015

At the start of April 2015, there were 226 Temporary Speed Restrictions (TSR) on Network Rail infrastructure. As of 9th October (end of week 3, Period 7) there were 331 TSRs on the network.