Railways: Environment Protection

(asked on 12th November 2020) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, how many incidents of train delay were attributed to vegetation on each Network Rail Region in (a) 2019 and (b) 2020 to date.


Answered by
Chris Heaton-Harris Portrait
Chris Heaton-Harris
Secretary of State for Northern Ireland
This question was answered on 17th November 2020

The Office for Rail and Road (ORR) publish summary statistics on the number of delay minutes and their causes. These statistics can be found here:

https://dataportal.orr.gov.uk/statistics/performance/passenger-rail-performance/table-3184-delay-minutes-by-operator-and-cause-periodic/

The following data produced by ORR shows the number of incidents on the railway attributed to vegetation management failure in 2019 and 2020 (to date) by Network Rail Region:

Network Rail Region

2019*

2020 (to date)*

Eastern

174

145

North West & Central

147

112

Scotland

67

95

Southern

129

188

Wales & Western

193

115

*This data is aggregated from data for (4-weekly) railway periods and therefore does not align precisely with calendar years. 2019 data represents the time period from 06/01/2019 to 04/01/2020. 2020 data is from 05/01/2020 to 12/10/2020 (railway period 7, latest data available).

Source: Network Rail data