Question to the Department for Energy Security & Net Zero:
To ask the Secretary of State for Energy Security and Net Zero, what steps his Department is taking to reduce waiting times for new grid connections for businesses in West Yorkshire.
The Department is working closely with Ofgem, the National Energy System Operator, and the network companies on a suite of reforms to improve grid access and reduce connection times across Great Britain, including West Yorkshire. This includes reforming the connections queue to prioritise projects that are ready and needed, strategically planning and accelerating network investment, and addressing wider barriers to speed up new grid infrastructure build such as planning delays, and skills and supply chain constraints.