Question to the Ministry of Defence:
To ask the Secretary of State for Defence, with reference to the Answer of 15 April 2019 to Question 241447 on Radioactive Waste: Dalgety Bay, whether the first stage of the remediations has been completed; and whether the second stage remains on target to be completed in 2021.
The first stage of the remediation work has not been completed; however work is underway on the site, following the granting of a licence by the Scottish Environmental Protection Agency, which was granted on 17 May 2021.
The target remains to complete all work by September 2022.