Railway Stations: Access

(asked on 16th October 2017) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, how many planned station upgrades under Network Rail's Access for All scheme have been (a) cancelled during rail control period 5 and (b) deferred to rail control period in each region.


Answered by
Paul Maynard Portrait
Paul Maynard
Parliamentary Under-Secretary (Department for Work and Pensions)
This question was answered on 19th October 2017

No schemes under Access for All have been cancelled during Control Period 5. The construction of 26 stations has been deferred to Control Period 6 and these stations are in the following regions:

North West 1

North East 2

East 3

East Midlands 2

West Midlands 1

Wales 4

West 1

London 9

South East 3