M6: Repairs and Maintenance

(asked on 12th January 2026) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, whether National Highways undertook a detailed assessment of the potential to construct temporary slip roads to allow Junction 38 of the M6 (northbound and southbound) to remain open for the duration of the Lune Gorge bridge replacement works; and whether that assessment was completed before the current construction programme was designed and approved.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 20th January 2026

National Highways first assessed the potential for temporary slip roads during the project’s optioneering stage in 2019. Further consideration took place during early design development, and the option was not taken forward at that time due to spatial constraints, value for money considerations, the need for significant lane and speed restrictions, and the likelihood of a costly extension to the overall construction period. The construction programme and design was then taken forward on that basis.

In 2025, following engagement with local stakeholders, National Highways committed to revisit this option, with a feasibility exercise carried out in August 2025. This re-considered the option of temporary slip roads. The exercise supported the conclusions during the early design phase; specifically, that temporary slip roads were unsuitable due to the space needed to construct the bridge decks, as well as representing poor value for money. During 2025, the programme assessed a wide range of options to improve connectivity, and resulted in the decision to defer work on Lawtland House bridge to a future date, improving local connectivity during the construction period.

When National Highways presented their findings from the feasibility exercise, a revised construction methodology was submitted by BWB Consulting on behalf of local stakeholders in October 2025. National Highways has committed to review this proposal from BWB consulting to see if it has presented an alternative viable solution. The review will conclude in January 2026.

Reticulating Splines