Nuclear Weapons: Military Bases

(asked on 30th January 2020) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, pursuant to the Answer of 24 January to Question 3807 and with reference to the key findings on page 7 of the NAO's report entitled Managing infrastructure projects on nuclear-regulated sites, published on 10 January 2020, which projects managed by his Department funding will be re-allocated from to fund the £1.35 billion combined cost increase in respect of the three projects examined by the NAO.


Answered by
James Heappey Portrait
James Heappey
This question was answered on 5th February 2020

The £1.35 billion cost increase reported in the NAO publication 'Managing Infrastructure on Nuclear-Regulated sites', represent the difference between initial cost estimates and the latest position for the projects reviewed. These costs have been absorbed and accounted for through business as usual budgetary processes within the Enterprise.