Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, what is the estimated strike rate for Hinkley Point C based on the annual RPI increases since the 2013 agreed strike rate of £92.50.


Answered by
Graham Stuart Portrait
Graham Stuart
This question was answered on 13th December 2022

The current strike price published by the Low Carbon Contracts Company (LCCC) is £106.12£MWh.