Radioactive Waste: Dalgety Bay

(asked on 9th October 2020) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, on what date his Department submitted an application to Scottish Environmental Protection Agency for the requisite licence to commence remediation works of the Dalgety Bay contaminated shoreline site for work scheduled to begin in summer 2020.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 14th October 2020

The Ministry of Defence (MOD) is not the authority responsible for applying for a licence to Scottish Environmental Protection Agency (SEPA) to commence remediation works at Dalgety Bay, the responsibility lies with the MOD Prime Contractor to whom the Final Contract Award was made in February 2020.

The Prime Contractor is intending to submit an application to SEPA by the end of November 2020.